Laying of internal partitions in apartments is underway in the fourth stage in section G-1
RIEL Real Estate Corporation reports that in the apartments in section G-1 of the fourth stage of the Novyi Fort. Mistechko Pidzamche Residential Complex, the laying of internal partitions continues. At the same time, in section G-2, the laying of chimneys has been completed. Also, the builders have begun installing entrance doors in all buildings.
In the third stage of the complex, in section V-1, the arrangement of the metal façade is being completed. At the same time, the installation of entrance groups in all buildings is underway.
In section V-3, preparatory work is underway to install power lines inside the building, and the water supply and ventilation networks are at the final stage of installation. At the same time, the installation of a metal roof covering is nearing completion.

For detailed information on the choice of floor and layout, as well as the terms of purchasing an apartment in the Mistechko Pidzamche Residential Complex, please contact our sales department. Contacts are available at the link.