Mistechko Pidzamche RC: in section V-4 of the third stage of Novyi Fort complex, the floor slab of the sixth floor is in progress
RIEL Real Estate Corporation reports that construction work of Mistechko Pidzamche RC is actively pursued. In section V-4 of the third stage of Novyi Fort complex, the floor slab of the sixth floor is in progress. This was announced by the head of the construction project.
In sections V-2 and V-3 the laying of the outer walls is under way.
It is also reported that in section V-2, the arrangement of the vertical structures of the seventh floor, and in section V-3, the floor slab of the seventh floor are being performed.
Besides, we would like to report that the installation of roof structures has begun in section V-1.
To choose the floor and layout, to learn more on the terms of purchasing an apartment in Mistechko Pidzamche RC – in the sales departments of the company. Our managers will be happy to advise you on any issue. Contacts at the link.