Fourth Stage Construction Update – June

July 16, 2026

Construction work is continuing on the fourth stage of the Mistechko Pidzamche. Novyi Fort residential development. In Building G2, installation of the metal roof covering has been completed. Finishing works are currently underway in the communal areas, while façade works continue on the Volynska Street elevation.

In Building G3, finishing works in the communal areas have now been completed.

Installation of the lifts has also been completed across all buildings in the fourth stage.

In addition, landscaping works have commenced across the development.

Mistechko Pidzamche. Novyi Fort residential development forms part of RIEL’s large-scale project in Lviv, creating a new residential neighbourhood close to the city centre. Contemporary architecture, on-site commercial amenities and thoughtfully designed public spaces combine to provide a comfortable and convenient living environment.

For further information about the available apartments and purchase options, please contact one of RIEL’s sales offices.

We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
Join our social networks
Contact us in convenient way
The exchange rate as of 10/19/2026 is 44.94 UAH.
Sales departments
Lviv, 116, Bohdana Khmelnytskoho Street
Lviv, Striyska str. 45
Constructors

ЧП «Львівінтерсервіс»

ООО «Вежа на Хмельницького»

ООО «Брама на Хмельницького»

© 2026  Pidzamche. Novyi Fort. All rights reserved.Privacy policy
Made in WEZOM
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.